Cheshire East Council is to carry out essential maintenance on the footbridge crossing the Silk Road, Macclesfield, starting July 24 and remaining in place until August 30.
In order for the work to be carried out safely, road closures will be put in place as follows:
Phase 1: 24 July to 11 August, southbound carriageway closed between Flash Lane Roundabout and Brockhurst Roundabout between 9.30am and 15.30pm. One of two lanes will be open during off-peak hours only between 24 July and 11 August. A signed diversion route will be in place via:
B5091 London Road, A538 Manchester Road, A538 Beech Lane and A537 Hibel Road.
Phase 2: 12 August to 30 August, the northbound carriageway will be closed between Brockhurst Roundabout and Flash Lane Roundabout from 9.30am until 15.30pm. One of two lanes will be open during off-peak hours between 12 August and 30 August. A signed diversion route will be in place via:
A537 Hibel Road, A538 Beech Lane, A538 Manchester Road and B5091 London Road.
Advanced signage will be positioned for all the works taking place, including variable message signage at key points to advise members of the public. Emergency vehicle access will be maintained at all times and local businesses remain open as usual.
On-site personnel will be on hand to provide any help and advice to the public.
Delays are inevitable but the council’s highways service has scheduled this work to be carried out during the school holiday period to minimise any delays and congestion.
All roadworks, closures and diversions associated with the project are displayed on the council’s online map at: